Check the "Contract Updates for the Week"

KOHL CENTER RESTROOM PARTITIONS

(contract last updated 01/20/2017)

SCOPE: Contract for the purchase of Kohl Center Restroom Partitions.

CONTRACT # DESCRIPTION
17-5737 KOHL CENTER RESTROOM PARTITIONS
CONTRACT ORIGIN: ADDITIONAL INFORMATION:
UW-Madison 
Purchasing Services
21 N Park St, Ste 6101
Madison, WI 53715-1218
UW-Madison users contact: 
Brad Bauman 
(608) 265-1462 FAX (608) 262-4467
brad.bauman@wisc.edu
  Non-UW-Madison users contact: Vendor Representative
RESTRICTED TO: University of Wisconsin Madison
COOPERATIVE PURCHASING: NO
CONTRACT TERM: December 1, 2016 through November 30, 2017, with automatic renewal extensions to November 30, 2020, unless amended, cancelled or rebid.

Manufacturer: SCRANTON PRODUCTS
Vendor(s)
101593
LaForce Inc
2602 Agriculture Dr
Madison, WI 53718
     
Sales Representative: PHONE # FAX #
Mike Morse 608-222-2424 ext. 1421 608-222-3916
E-mail mjm@laforceinc.com
  PHONE # FAX #
Ordering/Expediting: 608-222-2424 ext. 1421 608-222-3916
Invoice Information: 920-490-2360 920-491-2700
Returns: 608-222-2424 ext. 1421 608-222-3916
Supplier Diversity Reporting: 920-490-2389 920-491-2700
Website: www.laforceinc.com
Commodity Code 670-66
Federal Employee ID # (FEIN) 39-0980509
F.O.B.

“I” F.O.B. DESTINATION AND INSTALLED

“V” F.O.B. SERVICE/MAINTENANCE
Terms: N/30
Delivery: Installations will be done once each fiscal year for five years.  Year one will be Spring 2017, years 2-4 will be in July/August of 2017, 2018, 2019 and 2020.  Firm dates will be negotiated between the contractor and Athletics.
Warranty: Contractor will honor, at a minimum, the manufacturer's standard warranty on items and/or parts purchased under this contract.
Invoicing: Invoices shall reflect contract pricing.
Back Orders: Will notify ordering department within five (5) working days of order/release.
Back Orders: Will notify ordering department within 24 hours of order/release.
Other: Pricing not available to: University of Wisconsin System campuses, State of Wisconsin Agencies and Wisconsin Municipalities.
Pricing Information: SEE BELOW

Item

Description

Level / Stalls / Urinal Screens

Unit Price

1

Arena Control-M

Service / 1 / 1

$1,355.00

2

Arena Control-W

Service / 2

$1,688.00

3

Locker Rm 1

Service / 2

$1,928.00

4

Locker Rm 2

Service / 2

$1,644.00
5 WBB Service / 2 $1,674.00
6 WBB Coaches Service / 1 $850.00
7 MBB Service / 2 / 1 $2,033.00
8 MBB Coaches Service / 1 $1,232.00
9 Fetzer-M Service / 3 / 1 $2,837.00
10 Fetzer-W Service / 16 $13,750.00
11 Locker Rm 3 Service / 2 $2,053.00
12 Locker Rm 4 Service / 3 (2 stalls) $2,053.00
13

Officials

Service / 1 $828.00
14 103-M 1 / 3 $2,871.00
15 105-W 1 / 15 $13,315.00
16 111-W 1 / 15 $13,315.00
17 113-M 1 / 3 / 1 $3,333.00
18 117-M 1 / 3 / 1 $3,333.00
19 119-W 1 / 15 $13,315.00
20 125-W 1 / 15 $13,315.00
21 127-M 1 / 3 $2,871.00
22 202-M 2 / 2 $2,053.00
23 203-W 2 / 10 $8,960.00
24 205-W 2 / 10 $8,890.00
25 206-M 2 / 2 $2,053.00
26 210-M 2 / 2 $2,053.00
27 211-W 2 / 10 $8,890.00
28 213-W 2 / 10 $8,890.00
29 214-M 2 / 2 $2,075.00
30 216-M 2 / 2 $2,075.00
31 217-W 2 / 10 $8,890.00
32 219-W 2 / 10 $8,890.00
33 220-M 2 / 2 $2,053.00
34 224-M 2 / 2 $2,053.00
35 225-W 2 / 10 $8,890.00
36 227-W 2 / 10 $8,890.00
37 228-M 2 / 2 $2,053.00
38

NJP-M

2 Stalls

1 / 3 $2,053.00
39

NJP-W

7 Stalls

1 / 6 $6,657.00

 

SPECIFICATIONS

Seeking replacement of all toilet partitions at the Kohl Center.  The pricing is for the full project but will be implemented over a 4-year time span, installing ¼ of the restrooms in the building per year until project is complete.

The partition material will be Scranton Products solid plastic 1” HDPE partitions. The color will be a custom extrusion of “Duralife Lockers RED”.

 

The partitions will be overhead braced and floor mounted using existing wall brackets and standard aluminum latches and 8” wrap around hinges.

 

Installer will remove existing partitions and recycle if possible, remove existing TP holders, grab bars, and napkin dispensers, and re-install on new partitions. Installer will also furnish and install new grab bars to bring our ADA toilet compartments to current ADA requirements.

 

Project payments will be made in 4 total payments over the life span of the project. An individual payment will be made upon completion of one of the 4 individual installations.

Revision History

link to top of document