Check the "Contract Updates for the Week"

Click here for Piggybacking data form

BOILERS  INCLUDING INSTALLATION AT UW MADISON UNIVERSITY APARTMENTS

(contract last updated 03/08/2013)

SCOPE: Contract for the purchase of Boilers including installation.

CONTRACT # DESCRIPTION
13-5602 BOILERS  INCLUDING INSTALLATION AT UW MADISON UNIVERSITY APARTMENTS
CONTRACT ORIGIN: ADDITIONAL INFORMATION:
UW-Madison
UW Housing Purchasing Office
625 Babcock Drive
Madison, WI 53706
UW-Madison users contact:
Donald Schwoerer
(608) 262-2525 FAX (608) 265-8721
donald.schwoerer@housing.wisc.edu
  Non-UW-Madison users contact: Vendor Representative
COOPERATIVE PURCHASING: YES
CONTRACT TERM: March 15, 2013 through March 14, 2014, with automatic renewal extensions to March 14, 2016, unless amended, cancelled or rebid.

Vendor(s)
132069
Cardinal Heating
222 Linnerud Rd
Sun Prairie  WI 53590
     
Sales Representative: PHONE # FAX #
Craig Ouimette 608-837-9367 608-837-6469
E-mail craig@cardinalhvac.com
  PHONE # FAX #
Ordering/Expediting: 608-837-9367 608-837-6469
Invoice Information: 608-837-9367 608-837-6469
Returns: 608-837-9367 608-837-6469
Supplier Diversity Reporting: 608-837-9367 608-837-6469
Website: www.cardinalhvac.com
Commodity Code 920-12
Federal Employee ID # (FEIN) 39-1715610
F.O.B. “I” F.O.B. DESTINATION FREIGHT PREPAID INCLUDED AND INSTALLED
“V” F.O.B.  SERVICE/MAINTENANCE
Terms: N/30
Delivery: 5 days ARO
Warranty: 12 Year Heat Exchanger Warranty on Boilers
Invoicing: Invoices shall reflect contract pricing.
Return Policy: Contractor will provide for return of items ordered in error for up to 30 calendar days from receipt with the University paying only the return shipping costs.
Pricing Information: SEE BELOW
ITEM

DESCRIPTION

UNIT PRICE

 

LOT 1

 

1

Model – EL-150 Elite boilers

$4,900.00

2

SSU-119C gallon dual coil water storage tank

$4,676.00

3

UP26-99-F pumps

$340.00

4.

Badger meter recordall cold water bronze disc meter

$110.00 

5

HTX-60 Expansion tanks

$131.00

6

BB-30 Boiler Buddy

$875.00

7

Condensate neutralizer

$140.00

8

Fernox TF1 magnetic filter

$340.00

9

Grundfos Magna 32-120 house pump

$1,075.00

10.

 Other components required for full insullation including but not limited to new gauges and valves

$5,300.00

 11

 Lineal foot cost to pipe from soft water line to boiler make-up (20 ft. amount is for bidding purposes only, actual quantity will vary depending on specific installation)

 $12.50

 12

 Labor to include  disconnection, removal and disposal of existing boiler, water heater (if applicable), and components.  Installation of temporary domestic water heater, as required.  Full installation of boilers, make-up water loop, and components.  Startup.  Include flushing out system with Hydro-Solv 9100 (Rhomar) and treating with Pro-Tek 922 (Rhomar) ot arive at PH in rage of 7 to 8.5

$5,740.00 

 

 

 

 

LOT 2

 

13

Model EL-220 Elite Boilers

$5,600.00

14

SSU-119C Gallon dual coil water storage tank

$4,676.00

15

UP26-99-F pumps

$340.00

16

Badger meter recordall cold water disc meter

$110.00

17

HTX-60 Expansion tank

$131.00

18

BB-30 Boiler Buddy

$875.00

19

Condensate Neutralizer

$140.00

20

Fernox TF1 magnetic filter

$340.00

21

Grundfos Magna 40-120 house pump

$1,850.00

22.

 Other components required for full installation including but not limited to new gauges and valves

$5,300.00 

23.

 Lineal foot cost to pipe from soft water line to boiler make-up (20 ft. amount is for bidding purposes only, actual quantity will vary depending on specific installation)

$12.50

 24

 Labor to include disconnection, removal and disposal of existing boiler, water heater (if applicable), and components.  Installationof temporary domestic water heater.  Full installation of boilers, make-up water loop, and components.  Startup.  Include flushing out system with Hydro-Solv 9100 (Rhomar) and treating with Pro-Tek 922 (Rhomar) to arrive at PH in range of 7 to 8.5 

$5,740.00

 

 

 

 

LOT 3

 

25

Model EL- 399 Elite boilers

$10,150.00

26

SSU-119C gallon dual coil water storage tank

$4,676.00

27

UP26-99-F pumps

$340.00

28

Badger Meter Recordall Bronze Cold Water disc meter

$110.00

29

HTX-60 Expansion tank

$131.00

30

BB-80 Boiler Buddy

$1,300.00

31

Condensate neutralizer

$140.00

32

Fernox TF1 magnetic filter

$340.00

33

Grundfos Magna 65-120F house pump                    

$3,150.00

34.

Other components required for full installation including but not limited to new gauges and valves.

$5,600.00

35.

Lineal foot cost to pipe from soft water line to boiler make-up (20 ft. amount is for bidding purposes only, actual quantity will vary depending on specific installation)

 $12.50

36.

Lineal foot cost to pipe from soft water line to boiler make-up (20 ft. amount is for bidding purposes only, actual quantity will vary depending on specific installation)

 $61.00

 

 

 

 

LOT 4

 

37.1

 Per hour rate for repairs to existing atmospheric or high efficiency boilers (these repairs must be completed within 4 hours of initial call)

 $95.00

 

 

 

 

LOT 5

 

38.

 Per boiler cleaning and inspection service for high efficiency boilers from 80K through 399K BTU’s

$140.00

 39.

Per boiler cleaning and inspection service for atmospheric boilers from 500K through 1,500K BTU’s

 $140.00

SPECIFICATIONS

  1. Contractor must provide schedule for each installation which must be followed by all trades. If issues arise, any deviation from the schedule must be communicated to University Apartments project coordinator.
  2. Subcontractors must abide by all terms, conditions, and specifications under the contract.
  3. Contractor to introduce primary and all subcontractor foremen to University Apartments project coordinator prior to the start of their portion of the work.
  4. Review project spec and this list with subcontractors and installers.
  5. Contractor to install system per manufacturer’s recommendations.
  6. Existing horizontal hot water storage tanks to be abated by others, if applicable.
  7. Do not start work or set up in any mechanical room without notifying Apartment Facilities at least 30 hours in advance.
  8. Boiler replacements must be completed in a timely manner.  Contractor to provide temporary domestic water heater, if required to meet requirements below. The building affected cannot be without hot or cold domestic water or hot water for space heating (in heating season) for more than 8 hours at a time.  Apartment Facilities must be notified at least 30 hours in advance of any shutdowns.
  9. Keep hot water boiler piping separated to allow for 1 1/2 inch insulation (3” minimum clearance).  Make up water pipe insulation is 0.5” (1” minimum clearance).
  10. Allow maximum headroom clearance for all installations (consult with Apartment Facilities).
  11. Allow working clearance for valve handles, gauges, pumps, etc.
  12. Keep boilers and piping away from electrical panels, meters, etc. per NEC.
  13. Contractor to provide and install pressure gauges across circulator pumps.
  14. Contractor to provide and install circuit setters, if appropriate, and strainers on the return piping per manufacturers requirements.
  15. Contractor to provide all necessary electrical work for proper installation.
  16. Contractor to provide steel support stand under new boilers that will adequately support the boilers, associated components and piping raising the boilers off the floor between 14” and 20”.  Cut boiler support frame legs to fit floor slope rather than shimming legs and galvanize paint touch-up (3” adjustable feet are acceptable).
  17. Support PVC supply and exhaust piping inside mechanical room as close to existing stack as possible to avoid loading rooftop stack which is not able to support loads.
  18. Galvanize pipe straps exposed to weather; galvanize paint boiler support frames and miscellaneous steel (3 mil minimum coating of ZRC cold galvanizing compound available at LW Meyer-Madison) and finish coat with black enamel.
  19. Use unistrut plastic end protectors at all exposed ends where a person may come into contact with sharp ends.
  20. Debur all miscellaneous support steel and galvanize paint touch-up.
  21. Mount temperature sensor on exterior roof soffit and shield if exposed to direct sunlight.
  22. Re-install all domestic water circulation pumps (or install owner-provided pump).
  23. Position piping temp sensors downstream from delta T’s.
  24. Do not use die cast electrical conduit fittings.
  25. When flex conduit is necessary, use only galvanized steel flex conduit (not aluminum).
  26. Provide individual disconnects for each pump motor and label which motor is controlled.
  27. Provide ground wire in conduit to exterior sensor and as required elsewhere.
  28. Flush cut and grind all abandoned in-slab conduit.
  29. Provide unions at all pressure reducing valves and water storage tanks.
  30. Provide bypass piping at make-up water supply.
  31. Verify that all pumps and controls are working properly immediately after installation is complete.
  32. Check carefully for pipe leaks prior to leaving the site after start up.
  33. Call Police and Security (262-4524) prior to covering smoke and heat detectors and after removing the covering on these devices. 
  34. All abandoned pipe, hangers and supports to be removed by applicable trade.
  35. Use rubber “boot” type seals at roof stack PVC exit (provide submittal).
  36. Provide and install a sheet metal cap on outside air intake duct inside mechanical rooms.
  37. Seal existing stack inside mechanical room where PVC pipe enters (if applicable).
  38. The User agency may choose to save salvage items (water heaters, gauges, valves, pumps, etc.).
  39. Provide copies of State of Wisconsin Boiler Inspection forms for User Agency files.
  40. Provide factory approved start up of each boiler set; include copies of printout from combustion analysis.
  41. Contractor must provide designated campus personnel with instructions and training on operation of all systems installed.
  42. Work will be considered Substantially Complete when all equipment and installations are approved and accepted by User Agency.
  43. Contractor must provide at no additional cost, a follow up inspection within 3 weeks of each completed installation. Contractor must set up dates and times with the University Apartments project coordinator.

 

The following is additional specification for Lot 3 only.
44.  If existing stack is utilized for intake/exhaust, floor pipe supports shall be provided to carry load of pipes in stack.


Revision History

link to top of document