Procedure: 403.A-Calculating Rates for Revenue Producing Activities (RPA)

Appendix 1 Schedule XII

Final Unit Rate Calculation

Composite Rate per Unit (From Schedule XI)

$37.92

*Direct Materials (4 Sheets film @ $1.00 each)

4.00


Total Direct Cost Per Unit

$41.92

Overhead @ 44% of MTDC (if applicable)

18.44


Final Rate Per Unit

$60.36

*Direct materials are those which are used in a quantity directly related to number of units produced. They either become part of the finished product, or are consumed in the production process in a measurable amount per unit. Thus direct materials are not included in the hourly rate calculation, but are added later on a per unit basis.